Safety at Every Stage: Novisal Supports the Demolition of Brookhaven’s Iconic Water Tower

Site safety support for a complex infrastructure transition at an active federal laboratory.

For 85 years, Brookhaven National Laboratory’s iconic water tower stood above the campus in Upton, New York. Bringing the aging structure down meant more than removing a familiar landmark: it required careful coordination to protect workers, nearby infrastructure, and the laboratory’s ongoing operations.

On September 19, 2026, the 124-foot-tall, 300,000-gallon tower was demolished. Novisal provided site safety support to Yannuzzi Group, the industrial demolition subcontractor responsible for the mechanical dismantling and controlled knockdown.

A Historic Landmark Makes Way for Modern Infrastructure

Originally built in 1941 for the U.S. Army’s Camp Upton, the riveted steel tank later served Brookhaven National Laboratory. Over time, severe corrosion, structural deterioration, and mounting maintenance and sanitary challenges made replacement necessary.

A new 500,000-gallon elevated water storage tank was constructed adjacent to the original structure. The phased project encompassed new tank construction, removal of the vintage tower, and site restoration, while maintaining essential water service for the campus.

Novisal’s Role in a Coordinated Demolition Effort

Novisal provided site safety support to Yannuzzi Group as the demolition team worked alongside Brookhaven’s Modernization Project Office. Yannuzzi handled the specialized high-reach mechanical dismantling and controlled knockdown, using heavy excavators equipped with hydraulic shear attachments. 

The broader infrastructure transition operated within the laboratory’s regulatory oversight and Integrated Safety Management System (ISMS). Engineering and architectural work was handled by H2M architects + engineers.

Three Safety Challenges Behind the Demolition

1. Protecting an Active Campus

With the new tank immediately adjacent to the aging structure, strict exclusion zones and careful planning were essential parts of the project. The work had to avoid accidental impacts or vibrations that could compromise the weakened tower while protecting surrounding operations.

2. Managing Lead, Asbestos, and Dust

The tower’s historic coatings and insulation introduced hazardous-material concerns. The project’s mitigation measures included pre-demolition testing to identify lead and asbestos, certified abatement teams using spot containment and removing hazardous materials from critical cut locations and misting and dust suppression during dismantling.

These measures addressed airborne dust and potential ground contamination. They were part of the wider project’s environmental health and safety controls.

3. Addressing Structural Deterioration and Work at Height

The combination of the tower’s height and severe corrosion made conventional scaffolding and prolonged worker exposure at high elevations unsafe. The project instead used an engineered, controlled knockdown with specialized hydraulic heavy equipment. This approach reduced the need for extended manned work on the deteriorated structure and focused on protecting personnel and nearby active laboratory infrastructure.

A Safe Transition to the Next Chapter

The project record reports that the new 500,000-gallon tank was brought online and the original tower dismantled with zero safety incidents. Behind that outcome was a coordinated effort spanning infrastructure planning, hazardous-material mitigation, specialized demolition, and site safety support.

For Novisal, this project highlights its site safety role in a demanding demolition environment: supporting Yannuzzi Group as an 85-year-old landmark was removed beside active laboratory infrastructure.